Infrastructure approval timelines cut by up to 20 weeks for major projects
Threshold for major transport, water and energy schemes raised to €500m under new rules
12 February 2026 | editor@irishrealestate.news
Changes to the State’s Infrastructure Guidelines will remove up to 20 weeks from the approval process for major capital projects, according to the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation, Jack Chambers TD.
The amendments apply to projects in excess of €200 million and form part of Action 23 under the Government’s Accelerating Infrastructure Report, published in December 2025. The reforms are designed to reduce administrative steps in the project lifecycle and accelerate delivery through the consenting and approval stages.
Under the revised procedures, the External Assurance Process will no longer be required for major projects seeking approval at Approval Gate 1. Instead, projects will undergo a time-bound internal assessment by the relevant Vote section within the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation (DPER) before progressing to the Major Projects Advisory Group.
In addition, projects at Approval Gate 2 will no longer require Ministerial sign-off. Approval at this stage can now be granted by the Accounting Officer of the funding department. Ministerial approval remains in place at Approval Gate 1 and Approval Gate 3.
The threshold for classification as a “major project” will increase from €200 million to €500 million for schemes in the transport, water and energy sectors. This change reduces the number of projects subject to the more intensive major project oversight regime.
The updated requirements took effect from 11 February 2026 and apply to all new public investment proposals from that date. Projects already in the system must comply with the revised requirements as they advance through the lifecycle.
A departmental circular issued on 11 February [below] confirms that the External Assurance Process for all government departments is being replaced with a streamlined, time-bound internal review, and that Approval Gate 2 ministerial approval is removed with immediate effect. The circular states that all departments, local authorities, the HSE and public bodies in receipt of Government funding are required to comply.
The Accelerating Infrastructure Report sets out 30 time-bound actions aimed at speeding up project delivery. Alongside changes to the Infrastructure Guidelines, measures include additional support from the National Development Finance Agency for project development, simplification of planning and regulatory consents, and enhanced coordination to align funding and delivery.
Minister Chambers said recent progress on procurement for MetroLink and the Greater Dublin Drainage scheme demonstrated momentum in infrastructure delivery. He said the latest changes would significantly reduce approval timelines and that further reforms are planned, including the forthcoming publication of Critical Infrastructure legislation to enable certain nationally significant projects to be fast-tracked through planning and licensing stages.
Under Pillar 3 of the Action Plan, the Government has committed to legislative, institutional and financial reforms to reduce fragmentation in the system, align planning and funding processes, and create a more predictable pathway for delivering critical infrastructure.
Further elements of Action 23, including guidance on timelines and maximum lengths for preliminary business cases, are to be addressed through a wider review of Public Financial Procedures.